extended deadline marker

Assaf FMember for 18 years 9 months
Created
2
4
0
Hi,
Is there an option for the deadline red flag to appear after a defined period of time from the deadline? not at the instant the activity has passed its deadline.

Thanks,
Assaf.

2 replies

Oldest first
  1. 0
    Trevor Rabey ·
    I answered this in microsoft.public.project
    Make a Milestone (duration = 0).
    Make the task a FS predecessor with some positive lag.
    Put the deadline on the milestone rather than the task.
  2. 0
    Trevor Rabey ·
    I answered this in microsoft.public.project
    Make a Milestone (duration = 0).
    Make the task a FS predecessor with some positive lag.
    Put the deadline on the milestone rather than the task.