How to show extended durations?

IT StudentMember for 23 years
Created
2
3
0
Hi,

With MSProjectXP, we cannot specify a project duration of greater than 100%. But what if a project extends beyond the expected duration? How can we show this project was extended in MSProjectXP?

Thanks,

IT_Student

2 replies

Oldest first
  1. 0
    Se de Leon ·
    IT Student,

    Try this.

    Update Tasks with progress.
    Check Split in progress task in Schedule Option.
    Set Status Date same as Current Date in Project Information Dialogue Box.
    Go to Tracking Menu, Update Project
    Click reschedule uncompleted work to start after your
    status date.

    Regards,

    Se
  2. 0
    IT Student ·
    Wow, thanks man.

    Problem is I have the XP version & I am new to MSProject.

    Can you pls. give me instructions which tell me step-by-step how to do this?

    Very much appreciated.

    IT Student.