MSP2003 Splits Milestones

Paul SmithMember for 19 years 8 months
Created
1
3
0
I have been using the "Reschedule uncompleted work after ..." feature to shoe true critical path into key milestones. If there is an intermediate milestone that gets shifted from before the status date to after it MSP has been converting it to a task and splitting it so the finish date only gets moved to the logical date.

How can I stop MSP from splitting milestones and just move them as is?

1 reply

Oldest first
  1. 0
    Paul Smith ·
    Sorry Guys, I figured it out for myself.

    The PM had been in and statused these milestones as x% complete of course this is wrong, milestones are either zero or 100%). MSP saw this to indicate a change of type to an activity (which can be x% complete) and slits it as it reschedules the finish date.
    I will be aware of this and test for it before doing this again.