Combine more projects in one view
In the Open Standard
George de GreefMember for 17 years 4 months
- Created
- 2
- 5
0
Dear all,
I’ve a problem with the following. I made a lot of schedules for different projects. At a later date I want to combine these projects to one file where I can see this.
Like the following:
I have one file whereto I link all my projects. Than I change the bar styles and so on. After that it is finished.
But a month later I have a new project to add to the list. When I than click insert -> project -> "the new project". MSP insert it as extra tasks of the lowest project in the file.
What do I wrong? Have one of you a answer for this?
Thanks,
George
I’ve a problem with the following. I made a lot of schedules for different projects. At a later date I want to combine these projects to one file where I can see this.
Like the following:
I have one file whereto I link all my projects. Than I change the bar styles and so on. After that it is finished.
But a month later I have a new project to add to the list. When I than click insert -> project -> "the new project". MSP insert it as extra tasks of the lowest project in the file.
What do I wrong? Have one of you a answer for this?
Thanks,
George
2 replies
Oldest firstLog in or join to reply