Actual duration versus planned duration
In the Open Standard
Rod CampbellMember for 19 years 2 months
- Created
- 5
- 5
0
Here is yet another one that is doing my nut in!
I have 8 days planned for an activity. The reality is that it has taken 10 days and we are only 50% complete. Now, when we reschedule the programme, there are 4 days left (50% of 8)to complete, but the ’actual duration’ still shows 4 days complete, not 10!!!!
Got me stumped, anyone know of a way to show the actual duration, not the mathmatical duration of % complete???
I have 8 days planned for an activity. The reality is that it has taken 10 days and we are only 50% complete. Now, when we reschedule the programme, there are 4 days left (50% of 8)to complete, but the ’actual duration’ still shows 4 days complete, not 10!!!!
Got me stumped, anyone know of a way to show the actual duration, not the mathmatical duration of % complete???
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?