Earned value analysis? Or not?
In the Open Standard
Andy ButlerMember for 18 years 3 months
- Created
- 6
- 4
0
I recently went for an interview as a Planner & was told in the interview that I would be expected to carry out EVA.
I got the job and now I’ve started I can see that the company does not load their plans with resources.
Can any one explain to me:
1. How I can perform EVA when their are no resources or costs in the programme?
2. How I can diplomatically explain to my new bosses that they are talking rubbish?
As far as i can see, the only analysis that I can perform is by comparing the scheduled progress with actual. i.e. by baseline comparison.
HELP
I got the job and now I’ve started I can see that the company does not load their plans with resources.
Can any one explain to me:
1. How I can perform EVA when their are no resources or costs in the programme?
2. How I can diplomatically explain to my new bosses that they are talking rubbish?
As far as i can see, the only analysis that I can perform is by comparing the scheduled progress with actual. i.e. by baseline comparison.
HELP
6 replies
Oldest firstLog in or join to reply