earned unit
In the Open Standard
Jason LIMember for 18 years 9 months
- Created
- 4
- 6
0
Dear planner,
I have a question, I have a schedule, if I add same resource for each activity, and each activity have different unit, how can I show the column with the unit I defined;
And how can i realize the function after I save the schedule as a baseline, when I update the schedule, there will be a column like earned unit will changed according to the percent finished of the activity.
Thanks
I have a question, I have a schedule, if I add same resource for each activity, and each activity have different unit, how can I show the column with the unit I defined;
And how can i realize the function after I save the schedule as a baseline, when I update the schedule, there will be a column like earned unit will changed according to the percent finished of the activity.
Thanks
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?