Earned Value Calculation in MSP 2003
In the Open Standard
Niek ZonneveldMember for 21 years 7 months
- Created
- 5
- 4
0
Anyone out there with experience in generating reliable EVA numbers straight out of MSP 2003?
I get no BCWP/EV for work accomplished ahead of the status date. According to the calculation model it should calculate BCWP = BAC * %complete and the status date should have nothing to do with it.
Am I going crazy or am I overlooking something?
Thanks,
Niek.
P.S. done all the regular checks, i.e. baseline, resources rates, EVA calculation settings, etc.
I get no BCWP/EV for work accomplished ahead of the status date. According to the calculation model it should calculate BCWP = BAC * %complete and the status date should have nothing to do with it.
Am I going crazy or am I overlooking something?
Thanks,
Niek.
P.S. done all the regular checks, i.e. baseline, resources rates, EVA calculation settings, etc.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?