Dear all,
is there a way to resore the original baseline in MS Project like in P3

Thanks

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Jack,
    at the difference of P3, MSP does not create the baseline as a second project; it does copy and paste the fields: Start, Finish, Work and Cost to Baseline Start, Baseline Finish, ...
    therefore, if you had not saved the baseline before the 1st update of the project, there is no way to restore it.
    Alexandre
  2. 0
    Trevor Rabey ·
    How about select all tasks, strip off all progress, save baseline, re-input all progress?
  3. 0
    Alexandre Faulx-Briole ·
    Trevor,
    good work-around!
    I would copy the actual data in a Excel sheet 1st of all!
    Alexandre