MPX conversion

Francis Moyalan, PMP,PMI-SPMember for 21 years 8 months
Created
3
4
0
Hi Guys,

Cold we maintain the logic links in MSP program on importing to Primavera Ver 6.0.

I was trying to convert .MPP file using P3 , but was unable to make the conversion as the said format was not compatible.

Could anyone advise on this?

Thanks.

3 replies

Oldest first
  1. 0
    Rafael Davila ·
    P6 should be able to read MPP files.
    P3 reads older MPX file format but not MPP, you need a converter to convert MPP to MPX.

    All file conversions can create problems but converting form MPX/MPP to P3/P6 is less problematic than going the other way. For example MS Project does not allows two links to the same predecessor while 3/P6 does. Therefore P3/P6 will have no problem with these links while MS Project will.
  2. 0
    Vladimir Liberzon ·
    Actually P3 has problems with converting MS Project mpx. That is why we created separate P3 mpx export/import.
    Besides it is necessary to avoid linking phases (summary tasks) in MS Project if it is planned to convert the schedules into other software.
    Best Regards,
    Vladimir
  3. 0
    Rafael Davila ·
    http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=4&Top=61372