Linking Summary bar

Ismail KhanMember for 17 years 11 months
Created
2
3
0
Dear Planners,

Many people say that in summary bars should not be linked with activities or to other summary bars. But no one can clearly explain what will the problem we will face when we do it. Please advice.

regards,

ismail

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Ismail

    You will lose criticality and the programme will not react to change realistically.

    So best not do it.

    Best regards

    Mike Testro.
  2. 0
    Ismail Khan ·
    thank you mike