Skip to content

Links shown on baseline bars?

Bo JohnsenMember for 20 years 7 months
Created
2
3
0
I’ve received a progress programme, done in MSP 2000, where the links on the Gantt chart is shown on the baseline bars(Baseline Start / Baseline Finish), instead on the normal bars (Start/Finish). Up to this point I’ve only seen them applied to the "Normal"-bars.

Can anybody explain this or is there some setting in MSP where you can choose to which bar/dates the links should be shown?

Regards,

Bo

2 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Bo,

    Format > Bar Styles

    And then see if Baseline is first on the list.

    Regards,

    Darren
  2. 0
    Bo Johnsen ·
    Hi Darren,

    Thanks, it worked. Knew the importance of sequence of bar styles with respect to what is shown for bars, but not that it also applied to links.

    Thanks,

    Bo

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?