Having Trouble with actual / remaining / total cost
In the Open Standard
Gary WhiteheadMember for 17 years 6 months
- Created
- 3
- 3
0
Running MSP 2007
I’m trying to use MSP to report Earned Value metrics, without resource loading it.
I thought I would enter costs as fixed costs, baseline, then at each update enter actual costs and adjust the remaining costs, much like I would enter actual duration, and adjust remaining duration.
But I can’t find a way to manually adjust the remaining cost.
It seems to work OK if I adjust the ’fixed cost’ column instead of remaining cost, but this feels like a bit of a fudge to me.
What am I missing?
Thanks,
G
I’m trying to use MSP to report Earned Value metrics, without resource loading it.
I thought I would enter costs as fixed costs, baseline, then at each update enter actual costs and adjust the remaining costs, much like I would enter actual duration, and adjust remaining duration.
But I can’t find a way to manually adjust the remaining cost.
It seems to work OK if I adjust the ’fixed cost’ column instead of remaining cost, but this feels like a bit of a fudge to me.
What am I missing?
Thanks,
G
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?