Driving calendars
In the Open Standard
Stuart AtkinsonMember for 22 years 9 months
- Created
- 2
- 4
0
Everyone,
I currently have a 14 day (7 day calendar-no BH holidays) running through Christmas. It is the last path on the network, barring a finish milestone for 'planned completion'. which is its successor. This milestone has a 5 day claendar. As the previpous 14 day task is showing a finish of 30/12/11 the milesone finishes at the same (not honouring its calendar). If it was to honour its calendar, it should read 09/01/12. Can anyone tell me how to make the succeeding task calendar be the driver in MSP 2007 Pro.
Thanks Stuart
2 replies
Oldest firstLog in or join to reply