Skip to content

Driving calendars

Stuart AtkinsonMember for 22 years 9 months
Created
2
4
0

Everyone,

 

I currently have a 14 day (7 day calendar-no BH holidays) running through Christmas. It is the last path on the network, barring a finish milestone for 'planned completion'. which is its successor. This milestone has a 5 day claendar. As the previpous 14 day task is showing a finish of 30/12/11 the milesone finishes at the same (not honouring its calendar). If it was to honour its calendar, it should read 09/01/12. Can anyone tell me how to make the succeeding task calendar be the driver in MSP 2007 Pro.

 

Thanks Stuart

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Hi Stuart,   I don't have

    Hi Stuart,

     

    I don't have 2007 so not 100% sure, but could this  be because a milestone has zero duration, and hence there is no work being done on the milestone during the non-work day of 30/12/11?

    What happens if you make the milestone a 1 day activity with a -1d lag?

  2. 0
    Mike Testro ·

    Hi Stuart As soon as

    Hi Stuart

    As soon as a predecessor task comes out of a none work period the successor task will drop into the first available work day available in its own calendar.

    A milestone - having no duration - will drop into a very small gap - even 1 second long.

    So make sure you calendars and work patterns are concurrent with no gaps.

    Also check what calendars are on the resources.

    Best regards

    Mike Testro.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?