Linking the same resource assigned to different sub projects
- Created
- 1
- 4
Hi there,
I currently have an overall project (design office) with 3 inserted sub-projects (project #, holiday schedule and off site visits). They are all outline level 1.
Under projects are obviously different project numbers and indented in that are further sub tasks. Holidays are shown as tasks in the same way and off site visits too.
Essentially I have
1) PROJECTS ---> 2) PROJECT # ---> 3)design/manufacture/assembly/track test
1) HOLIDAYS ---> 2) NAMES ---> 1/2/3
1) OFF SITE VISITS ---> 2) TRACK SUPPORT/COURSES ----> races/cities etc.
It I take Charli as an example. I would be assigned to 2 or 3 tasks within projects. I would also be assigned to my own holiday dates (set up as tasks) and perhaps to a few days on a course. In resource usage however the resources are displayed -
Charli - design 8 hours, scheduling 7 hours, manufacture 20 hours
Ben - production 8 hours
Rob - manufacture 20 hours, visits 25 hours
Charli - Holiday 1 - 450 hours
Ben - Holiday 1 - 200 hours
Charli - Silverstone - 16 hours
Although resource overallocation is shown for each 'Charli' seeing as there is only ONE charli, I need to arrange project to show this. Currently the 3 subprojects are linked as Start to Start. Resources are assigned from my email address book. You can see visually on the Gaant view that I am assigned 100% to more than one task... however I do not have room for visual errors and as such need for it to be highlighted in resource usage as an allocation for e.g. if holiday and tasks collide!!!
So how do I link the 3 subprojects and my resources?
Help muchly appreciated!
Thanks
Charli
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?