Skip to content

milestone tasks not displaying 0d and % complete

Kp RaoMember for 15 years 2 months
Created
1
4
0

Dear planners,

I have a strange situation.i am using ms project 2007.the problem is milestone tasks not displaying 0d and % complete.this is happening for few activites only.when i add new activities they are showing the 0d and %complete.

Any help

urgent

Thanks

kp

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    I use 2003, but i assume this

    I use 2003, but i assume this will be the same as 2007.

     

    If you go to the task information box for this "milestone", under advanced tab there is a check-box called "Mark task as milestone"

    If this is checked, the task will appear as a milestone on the gant chart even though it has a duration, % complete, resources, etc

     

    To correct, you can choose to either uncehck this ox and treat the task as an activity, or set the duratino to zero and treat it like a milestone.

     

    I have never understood why MS Project allows for this functionality. It seems quite peverse.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?