Summary duration % Complete

Ahmed KHRMember for 15 years 11 months
Created
2
3
0

Dear Planners;

I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!

 

So, Any body have an Idea about please share it.

 

Regards.

 

2 replies

Oldest first
  1. 0
    Ali Deveboynu ·

    % complete on summary task

    % complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30

    best regards

  2. 0
    Ahmed KHR ·

    Thank you Ali for the

    Thank you Ali for the confirmation.