Skip to content

Baseline Milestones

Philip KearneyMember for 24 years 7 months
Created
1
2
0

Hi, Has anyone come up with a way to show baseline milestones in MS PRoject as using MSP 2010 so when I baseline the schedule, tasks are the only one showing the baselines.

 

Tried to do it manually in the Bar Styles option to no avail!

 

Please reply with answer asap as desperate!

1 reply

Oldest first
  1. 0
    Michael Slawinski ·

    Philip, try this

    Philip,

     

    try this

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?