How to calculate % work done

Ashik GBMember for 15 years 10 months
Created
1
5
0

Hi Friends,

I have a small querry regarding how to get the information on calculation of Planned % work done for the particular month from Main Schedule.

For Ex: if the project duration is 365 days from Jan1st to dec31 st with 100% Scope, in that how can i know what is the planned % work for the month of any particular month?

 Please can any one help me for this?

Regards,

Ashik

 

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Ashikdisplay "Task Usage"

    Hi Ashik

    display "Task Usage" view, the set the time scale to month, right-click the distribution panel (rightmost panel), and select the "Baseline Work" field

    as MS Project does not have a "% planned work" field, you will have to compute the %tage by yourself

    Alexandre