Skip to content

EARLY START AND LATE START S-CURVE

Zuraini LazimMember for 20 years 2 months
Created
1
3
0

Hi,

Appreciate if somebody could show me how to fill up the early start and late start date columns as data cannot be entered and on ly show display dates that are similar to START and FINISH dates. I need these info to construct my early start and late start s-curve. I also noted that the milestone task early and late start dates will be the same as start and finish date. How to develop these early and late start dates for a project?

1 reply

Oldest first
  1. 0
    Izam Zakaria ·

    You can't simply fill up the

    You can't simply fill up the dates, it must came from the logic of activities....you have to establish 1st the project activity and form there the total float will define you the late start and finish....furthermore explanation, reach me at aizam.zakaria@yahoo.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?