Can MS Project change the % assignment, when doing resource leveling?
- Created
- 1
- 3
Hi, I am just wondering, whether MS Project can do the following:
Situation:
Task1 has priority 1000, duration 5 days (Mon-Fri) and resource A, assigned 50%
Task2, has priority 500, could start on the same Monday, has resource A assigned 100%. Task is effort driven.
As a result, before leveling, this schedule creates resource A over allocation (150%) for Mon-Fri.
What I want:
Is it possible to run resource leveling in a way, that will leave Task1 intact. Task2 will still start on Monday, but for 1st week will have Resource A work 50% on a task and the remaining 50% of work will move to the next week with 100% assignment (hence will finish somewhere on Tue).
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?