Baseline for MSP 2010
In the Open Standard
Kumar BaijuMember for 15 years 8 months
- Created
- 0
- 3
0
Hi Expert
I had ceated a schedule in MSP 2007 , In that i have set baseline, Baseline1, baseline2, baseline3. after some time my MSP 2007 has been updated with MSP 2010. In 2010 it shows that baseline has set (0,1,2,3) om different dates. but when i enter the colum of baseline it shoe base line date. but when i entered Baseline1, baseline2, baseline3 it shows NA in each activity. Please guide me how can i get the Baseline1, baseline2, baseline3 date.
Regards\\
KB
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?