Create an Indicator column in MS Project which measures the % complete vs % planned of each activity
- Created
- 5
- 5
Hi,
I have developed a project plan (which includes a % complete and a % planned column) and I wish to insert 3 types of indicators to show me how I am advancing with the progress of each activity:
Green: Shows the activity is on target
Yellow: Shows that the activity is between 1%-10% behind schedule
Red: Shows that the activity is greater than 10% behind schedule
I know how to insert the indicator but I don't know what formula I can use to calculate if i'm on target or behind schedule. Any ideas?
In case you are wondering, the % complete column I inserted comes by default in project, however, the % planned is a text column which I update by clicking on "upadate project" button on the project tab which automatically updated progress % of each activity. I then copy that information onto the % planned column.
Thanks
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?