Dear Planners,

I created a new calendar different from the standard calendar and I would like this calendar to be assigned to my project, in order to do that, in the project information window I changed the calendar from standard to the calendar I already created.

But, when I added a task calendar column in the gantt chart view, I got "None" under the task calendar, so I have to change it manually.

Best,

Moutaz

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Mountaz,"None" means that the

    Mountaz,

    "None" means that the task is using the project calendar; it is not necessary to assign the project calendar to tasks, except if you want the task calendar to manage a resource loaded task, instead of the resource calendar

  2. 0
    Moutaz Aldeib ·

    Thanks Alexandre for this

    Thanks Alexandre for this info, it is strange that the project calendar name is not mentioned in the task calendar column.

    Best,

    Moutaz