Calendar
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 2
- 2
0
Dear Planners,
I created a new calendar different from the standard calendar and I would like this calendar to be assigned to my project, in order to do that, in the project information window I changed the calendar from standard to the calendar I already created.
But, when I added a task calendar column in the gantt chart view, I got "None" under the task calendar, so I have to change it manually.
Best,
Moutaz
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?