Retreiving a baseline, export it to P6
In the Open Standard
Tim ReadmanMember for 23 years 4 months
- Created
- 1
- 5
0
i am a P6 user using MS projects and need help to export a baseline. i hope some planner out there will help as i rarely use the software.
I have been given a MS project file which has under it a baseline project and labled planned programme.
i have exported the project as and XLM to Primavera P6 quite successfully using Asta Powerproject as the interface.
This does not bring across the baseline project. is there away to save the baseline programme of this project as a standalone project which i could then export as i have done for the current project ?
Paul , Thank you for explaining that problem. I will have to get the baseline from the client server as I need the logic. very kind Regards Tim1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?