Skip to content

Actual Cost

Wadi El-Din HammoudaMember for 12 years 3 months
Created
0
5
0

Hi,

I'm updating the actual progress of a project during which i put the % complete of a task as 75%. i need to reflect this 75% on the actual cost of the task, but when i enter the 75%, the actual cost is calculated to be more of a 90% of the total cost. I only loaded a prorated material resource if this matters. How do i reflect the % complete entered to a task on the actual cost ?!

Thanks,

Wadi

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?