Hi !!

I want to make a calendar in MSP 2013 for which I copied the 24 hrs shift.

Now using exceptions I entered the 4 national holidays which went fine.

I marked all the sundays as Off. Now we have a shift change / off day every 15 days or on  the alternate sundays.

Can I do that using some command or I have to select every alternate sunday manually for the project duration ??

 

 

1 reply

Oldest first
  1. 0
    Shishir Dhatwalia ·

    I did it using the exceptions

    I did it using the exceptions tab

     

    made an exception called "Alternate Sunday"

    Then click - details; Non-Working radio button is selected &

    used the recurrence pattern.

     

    If any other method is there plz let me know.