Resource usage in a report
- Created
- 0
- 5
Dear All,
In a report I have included a table showing the tasks that a resource should be working on in a particular week. So open tasks per week per resource.
When possible I would like to extent that table with the amount of hours a resource should be spending on a task in that week.
Is there a field for this? Or how can I make one? The work fields are all related to the task totals.
I am more lookig for resource usage per task per Week (or Month). So basically the resource usage view per resource with a time scale set to weeks and so showing the amount of hours per task per week.
The reason I would like to have that in a report rather than a seperate view (resource usage) is that in that case I only have to print the report I have prepared to have all information for a weekly/monthly progress meeting of various projects.
In addition one more question about how you can get a (print) date or the relevant weeknumber (or month) of a table printed in your report.
Many thanks in advance for all support.
Martin
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?