Driven predecessor in critical path
In the Open Standard
Lo GaryMember for 16 years 8 months
- Created
- 2
- 6
0
Dear all readers,
In Microsoft Project 2007, there was a function which enable us to know which predecessor out of other predecessors is driving the critch path, this function is no longer exists in later version.
Could anyone teach me, if I want to squeeze the critical path, and I trace back from the completion date backwards. However . some task have many predecessors and could I know which one is driving rather than I have to squeeze all predecessors.
Thank!
Regards,
Gary