Gant baseline and actual date icons for each task
In the Open Standard
Joshua TophamMember for 6 years 11 months
- Created
- 2
- 5
0
Hi, I have a very basic project with a list of milestones, all of which had baseline dates. For some milestones the baseline wasn't hit and we have later actual dates in another column. (Where there's no slip the baseline and actual columns have the same date.) I'd really like to visualize this on the gant with a baseline icon as well as the actual one so the missed milestones were easy to see. Does anyone know if it's possible to add a second date icon to the gant view like this?