where is the switch to make % Complete change Remaining Durations? and vice versa

Rodney JonesMember for 14 years 4 months
Created
1
39
0

Hello All,

where is the switch to make % Complete change Remaining Durations?

 

My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?

1 reply

Oldest first
  1. 0
    Paul Harris ·

    In MSP the % Complete is

    In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.

    Regatrds

    Paul E Harris

    Eastwood Harris Pty Ltd

    www.eh.com.au