where is the switch to make % Complete change Remaining Durations? and vice versa
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 1
- 5
0
Hello All,
where is the switch to make % Complete change Remaining Durations?
My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?