Shared mode
In the Open Standard
Nick JacksonMember for 19 years 3 months
- Created
- 6
- 6
0
Hi
Got a stange one. I'm running standalone as follows:
About: Primavera P6 Professional 24
Release: 24.12.0.51267
Platform: x64
Database Schema Version: PPMDB,2412.0000.0000.0006
PPMDBSQLite.db
Every time I schedule the shared mode warning comes up. No one else uses the database (its standalone). I don't appear to have the 'access' option which lets me choose shared or exclusive use.
I logged out and even tried re-booting.
Anyone know how I can stop this message - its not fatal but very irritating.