P3e WBS Filter

Alan ChadwickMember for 23 years 3 months
Created
3
3
0
Is it possible within the project WBS screen to run a filter that only display a particular node or is this another function due for release in version 5, 6, 7 8 etc



3 replies

Oldest first
  1. 0
    Paul Harris ·
    Create a filter with WBS equals & the value you require.

    In Group & Sort you will need to select the option “Hide if empty” to hide the WBS bands that do not have activities displayed.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au


  2. 0
    Alan Chadwick ·
    Paul,

    Think your reply infers that i am in the activity view....i want to view a single node on a pretty large programme (multi project)so that i could pull out the WBS structure for a particular project within the WBS view.

    Alan
  3. 0
    Paul Harris ·
    Alan

    Then I think the answer is no.

    I agree with your concept, I think you should hit the Help, Suggestion Box!… icon and send a suggestion to Primavera Systems

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Book Publishers, Training & Consulting
    www.eh.com.au

Log in or join to reply