cost : actual & budget

Amir DadbakhshMember for 22 years
Created
1
3
0
hi guys
I faced the problem and i need somebody to give me hand to solve my problem.
i work for oil company and our project contains about atleast 500 tasks.it,s really hard to write budget cost and cost at completion for each task especially we always face the change order that make change our cost at completion so Iam looking for a way to link enterprise and msp to transfer cost from msp to enterprise.
i would be really glad to have your advice on it.

1 reply

Oldest first
  1. 0
    Masoud Rahimian ·
    Dear Dadbakhsh
    why linking to MSP??you can link enterprise to MsSql Or oracle and Update any field automaticaly from your Company MIS or any Software.

    Masoud

Log in or join to reply