Start vs. Finish total float!

Nozar NaghaniMember for 22 years 3 months
Created
1
2
0
In P3e (advanced scheduling options), there are options for "Compute Total Float as":
1- Late start-Early start
2- Late finish-Early finish


I cant understand in which case, these two might differ and how we may benefit from this option.

Anybody there to give me an example?


Thanks
Nozar

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    1. Level Of Effort activities are entirely dependent upon which setting is used to compute float.

    2. Activities that are constrained by logic to their start as well as to their finish may show different float values depending upon this setting.

Log in or join to reply