P3EC Export as XER file Calendar Data Issue
In the Open Standard
John GriffithsMember for 21 years 9 months
- Created
- 4
- 1
0
Does anybody have any information that explains the method being used to store the exception information for non-working days that have been applied to a P3EC calendar when a project is saved in the XER format? The example below is part of the exceptions data in the calendar section of an xer file:
(0||Exceptions()
((0||0(d|36126)())
(0||1(d|36153)())
(0||2(d|36311)())
I am showing 3 of a total of 105 exceptions but have no idea what the 5 didgit number means.
Any help would be really appreciated. Thanks
(0||Exceptions()
((0||0(d|36126)())
(0||1(d|36153)())
(0||2(d|36311)())
I am showing 3 of a total of 105 exceptions but have no idea what the 5 didgit number means.
Any help would be really appreciated. Thanks
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?