Copy & Paste between programmes

Andrew EdwardsMember for 21 years 11 months
Created
7
5
0
Can anybody shed some light on the best way to do this? I know this is a stupidly simple question, but right now my colleague and I are at the end of our tether with it. We’ve tried almost every method we can think of, but still P3e stubbornly refuses to paste the copied activities into the destination programme.

Any help would be greatly appreciated.

Andy

7 replies

Oldest first
  1. 0
    Steven Oliver ·
    Open both Source and Target, select Project, Wbs and copy your source wbs to target.


    HTH
  2. 0
    Andrew Edwards ·
    Thanks Steven, does this work with partial sets of activities from the WBS?

    Andy
  3. 0
    Steven Oliver ·
    No, it will copy all activities. Just delete those you dont want. Or in your source project segregate the activities you want into a temp wbs, copy to your target and then move source activities back to the original wbs.

  4. 0
    Steven Oliver ·
    Incidentally, I’ve just copied activities in the activity view from one project to another without any trouble.

    You do have permissions for both projects, dont you ?
  5. 0
    Andrew Edwards ·
    Cheers Steven,

    Did you work at NR in York recently?
  6. 0
    Steven Oliver ·
    Guilty. But "work" and "NR" should never be used in the same sentence
  7. 0
    Andrew Edwards ·
    How very true. Given that I’m staff here, I really shouldn’t complain but.....