Enterprise resoruce levelling
In the Open Standard
Luca BasileMember for 23 years 3 months
- Created
- 13
- 4
0
We are trying to use P3ec for an enterprise resourcing exercise.
We succeed successfully to use roles and then switch to the single resource assignment, and have role and resource profiles.
We also succeed to resource level for the portfolio of selected projects … but P3ec is levelling only the resource associated with non critical activities and letting any over allocation associated with the critical path.
In the levelling form we flag out the “Level resources only within activity total float”,
we also prioritize the projects with “Project Levelling Priority” as per project importance but nothing change.
It seams it is able to level resource between projects only on the non critical activities.
Any one has before used P3ec for company resorucing purpose?
Any tips will be welcome.
Thanks
Luca
We succeed successfully to use roles and then switch to the single resource assignment, and have role and resource profiles.
We also succeed to resource level for the portfolio of selected projects … but P3ec is levelling only the resource associated with non critical activities and letting any over allocation associated with the critical path.
In the levelling form we flag out the “Level resources only within activity total float”,
we also prioritize the projects with “Project Levelling Priority” as per project importance but nothing change.
It seams it is able to level resource between projects only on the non critical activities.
Any one has before used P3ec for company resorucing purpose?
Any tips will be welcome.
Thanks
Luca
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?