Skip to content

Milestone Costs - P3 to P3e Conversion

Andy QuinnMember for 21 years 4 months
Created
2
1
0
Good afternoon all

I have a project in P3 which is resourced and cost loaded. There are also some finish milestone activities in this project which have budgeted costs assigned to them. So far so good.....

When I import this project into P3e the budgeted costs that were assigned to the milestones in P3 become budgeted expense costs in P3e. My standard activity costs become budgeted labour costs.

Does anybody know if there is any way of seeing the total budgeted cost for the project as an s-curve or can I only see labour resource graphs in P3e??

I can potentially work around this by making my P3 finish milestones 1 day activites so that once imported they become labour costs.

Has anybody else had this problem?? Any help would be greatly appreciated.

thanks

2 replies

Oldest first
  1. 0
    Kevin Button ·
    In activity view go to Activity Usage Profile. Then right click on the profile and select Activity Usage Profile Options. On the data tab, select to display Cost and then tick the Total check box to display a curve for all costs.

    Regards

    KB
  2. 0
    Andy Quinn ·
    Thanks Kevin

    Looks like I was looking at resource profile and not activity profile.

    Andy

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?