Milestone Costs - P3 to P3e Conversion
In the Open Standard
Andy QuinnMember for 21 years 4 months
- Created
- 2
- 1
0
Good afternoon all
I have a project in P3 which is resourced and cost loaded. There are also some finish milestone activities in this project which have budgeted costs assigned to them. So far so good.....
When I import this project into P3e the budgeted costs that were assigned to the milestones in P3 become budgeted expense costs in P3e. My standard activity costs become budgeted labour costs.
Does anybody know if there is any way of seeing the total budgeted cost for the project as an s-curve or can I only see labour resource graphs in P3e??
I can potentially work around this by making my P3 finish milestones 1 day activites so that once imported they become labour costs.
Has anybody else had this problem?? Any help would be greatly appreciated.
thanks
I have a project in P3 which is resourced and cost loaded. There are also some finish milestone activities in this project which have budgeted costs assigned to them. So far so good.....
When I import this project into P3e the budgeted costs that were assigned to the milestones in P3 become budgeted expense costs in P3e. My standard activity costs become budgeted labour costs.
Does anybody know if there is any way of seeing the total budgeted cost for the project as an s-curve or can I only see labour resource graphs in P3e??
I can potentially work around this by making my P3 finish milestones 1 day activites so that once imported they become labour costs.
Has anybody else had this problem?? Any help would be greatly appreciated.
thanks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?