Duplicate IDs
In the Open Standard
Tim DaviesMember for 21 years 1 month
- Created
- 11
- 2
0
I have been amending a copy programme to suit a new project, which has some repeated sections of work. The first thing I have done is amend the project WBS, deleting some branches and renumbering others.
The activity numbering has now changed within the project and I now have many activities with different activity names, but the same ID. As many as four, activities have the same ID. Some are sitting within the same WBS section, others in different sections.
How can this happen? What is the best way to sort this out?
The activity numbering has now changed within the project and I now have many activities with different activity names, but the same ID. As many as four, activities have the same ID. Some are sitting within the same WBS section, others in different sections.
How can this happen? What is the best way to sort this out?
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?