P3 - XER Conversion / XER Format

David BordoliMember for 24 years 6 months
Created
2
1
0
Hi All

I’m hoping a Primavera expert can offer some assistance to a Primavera dummy…

Is there such thing as P3 to XER file conversion utility – can I get hold of one? I have a client who uses P3e and I wasn’t to convert my P3 files so he can use it.

If there is no utility, or in addition, is there anywhere documented the technical specification of an XER format? I am thinking maybe our IT guys could cobble a conversion together for me.

Thanks

David

ps. I have taken the liberty of posting this message in the P3 forum too.

2 replies

Oldest first
  1. 0
    Joao Ribeiro ·
    Yes, they comes with P3e/c, one is called p330xerconvert.exe, the other xerp330convert.exe. If you instaled P3e/c you should have then under Commun files\convert. Primavera recomends using then for large schedules, instead of direct convertion.

    There is also an Excel woorksheet at Primavera’s costumer support for checking convertions and format.
  2. 0
    Ruel Llegado ·
    Mario is also correct.

    You dont need any software to convert P3 to .XER Format. Just open your P3e or P3ec, file, import...

    Goodluck.