MSP XML file will not import to P6 despite being correctly formatted
- Created
- 11
- 3
Hi all,
I'm really hoping someone can help.
I have managed to import several msp files (after converting them to xml) into P6 Professional 16.2 (EPPM). However, I've got four project files that just will not import. It gets to 50% and then drops out. Error message "job did not complete successfully".
There are no blank cells or links to summary bars in the msp files. The WBS has been correctly formatted and does not contain any gaps. The project summary bar is switched off and all of the projects have been properly aligned.
I am at my wits end trying to understand why these files won't import. Any ideas? All help gratefully received!
11 replies
Oldest firstLog in or join to reply