P3e advise for Beginner
In the Open Standard
Paula CohenMember for 21 years
- Created
- 1
- 4
0
A one minute lag seems to have been introduced into my schedule. I plan in days, with either a one-working day weekend or 5-working day mid-week calendar being assigned. The shift patterns are 08:00 – 17:00 for both. However activities with a one-day duration started extending over two dates. When I looked at the start and finish minutes, instead of starting at 08:00 the activity was starting at 08:01 and finishing the following day at 08:01. When this additional minute is manually removed the finish time reverts back to 17:00. My lag between activities is always in full days. The resources allocated to the activities also have the same shift times.
As I have only been doing P3 planning for a few months, this has stumped me.
Please help.....
As I have only been doing P3 planning for a few months, this has stumped me.
Please help.....
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?