P6 Beginner Question - Can i change the start day of the project ?

Shawkat MatarMember for 10 years 8 months
Created
2
2
0

Can i change the start day of the project ?

2 replies

Oldest first
  1. 0
    Irfan Khan ·

    Dear Shawkat, You can

    Dear Shawkat,

     

    You can chnage/Modify your start date @ anytime by following these steps :

     

    1 - open your project & go to Project Window

    2 - Click on Date Tab

    3 - You can see there an option "Project Planned Start" just change it to your desired date you want.

     

    hope this will help

     

    Regards,,,, 

  2. 0
    Zoltan Palffy ·

    you wil also want to change

    you wil also want to change your data date to equal your start date 