Convert P3.1 data to 4.1 (e&c)

Amar AghanaMember for 21 years 2 months
Created
2
2
0
Guys, I wish to convert around 200 Projects in 3.1 to 4.1.

I have done the following excersize.

1) Crated Resource, Calendar, EPS, OBS, Activity Code etc in 4.1

2) Changed Calendar, Resource, Activity Code of 3.1 similar to that of 4.1

3) Imported 3.1 project data to 4.1

4) The problem I faced is Calendar, Resource, Activity are crated again in 4.1.

Any suggestions pls?

2 replies

Oldest first
  1. 0
    Christian Adrian De Vera ·
    Amar

    Shengyun is right.. let all the datas from you 3.1 be exported to 4.1 just to make it more intact then try to compare you 4.1 vs 3.1 datas and see for yourself if they have the same datas, only then you can start modifying your projects.. hope this helps..

    Cheers!

    Christian
  2. 0
    Amar Aghana ·
    Shengyen, Christian, Thanks for the advice. I have new projects already created in 4.1. I need to import the existing projects from 3.1. I shall try keeping your suggestions in mind. Thanks.

Log in or join to reply