V5: Lost Data

Amar AghanaMember for 21 years 2 months
Created
23
6
0
Friends,

While working on the projects, unfortunately, I have deleted on resource.

This has deleted all resource loading connected with that resource in all projects.

Is there any way to restore the deleted resource back??

Urgent Help Required please

Regards, Amar

23 replies

Oldest first
  1. 0
    Amar Aghana ·
    I have logged in and Logged out. With this I think, I will not be use even undo function
  2. 0
    Kevin Button ·
    Amar

    Unfortunately I think your resource has gone for good, unless you have a backup of your schedule somewhere. If you do, restore the project and the resource will be put back into the pool.

    Regards
  3. 0
    Amar Aghana ·
    Kevin, Thanks. I think it has gone.

    I had saved PMDB and MMDB in server. When I copied the saved PMDB and MMDB to hard disk, I could not see the original data.

    What is the correct way of backing the data? Is it saving PMDB and MMDB or opening all projects and creating an XER file?

    HTH, Amar.
  4. 0
    Kevin Button ·
    Amar

    I like to create an XER file every day for the 2 projects I am working with, they zip up fairly small and it is easy to restore one or both projects if necessary. Because I work in a large company, the PMDB database runs on a dedicated server and the MSSQL software creates a backup every night, so I don’t have to bother with it.

    If you have a stand alone database you might consider a regular XER export, and a full PMDB/MMDB backup from time to time, just in case your PC has a really bad day. I have never used version 5.0 stand alone so I don’t know what is involved with backup/restore for a MSDE database. For that you will need to read the instructions which should be on the documentation CD.

    Hope this helps

    Cheers
  5. 0
    Amar Aghana ·
    Kevin, That is fine with me. I will do both. Cheers, Amar.
  6. 0
    Philip Jonker ·
    There is a possible answer, if information was imported, re-type the numerical fields
  7. 0
    Amar Aghana ·
    Yeah, This worked as even after deleting the resources, for imported projects, labour units were retained and I could retrieve the lost data. Thanks, Amar.
  8. 0
    Marcio Sampaio ·
    Dear all,

    For security of projects on my company, we program "job services" that crate back ups of all projects 2 times a day (every 08 am and 06 pm).

    Regards.

    Marcio Eduardo
  9. 0
    Amar Aghana ·
    Marcio, Can you please send the details or explain how you do this in Job services. I read in manual but not tried. - Amar.
  10. 0
    Marcio Sampaio ·
    Amar,

    First of all u have to install "Service Pack". I think u already did it

    Go to "Tools / Job Sevices";
    Click "Add", give it a name and on "Service Type" choose "Export";
    On "Job Datails" choose "Everyday at" (the time u want) and a place to create log file;
    On "Job Options" choose the project u want to create a .XER (u can also choose an EPS level, it will create a .XER for all projects under this EPS level);
    Still on "Job Options", choose the place to create .XER file.

    For more security, u can create two "Job Services", one in the morning and other in the end of work day (for example).

    I suggest u to do a test creating a "Job Service" (export)one hr after the time u create and check if it’s working.

    Sorry for my English.

    Glad to help.

    Marcio Eduardo
  11. 0
    Dinesh Kumar Damavarapu ·
    If I am not mistaken, your contract administator keeps regular back ups of the server database.Check with him and you can restore the database using the old data.

    Regards

    Dinesh
  12. 0
    Amar Aghana ·
    Dinesh, Theoritically you are correct. Unfortunately, my person washed hands after installing the software. According to him, once the software is installed, his duty ends.... They are still thinking V5 is like P3 only. Cheers, Amar.
  13. 0
    Amar Aghana ·
    Marcio,

    Still I have not tried your suggestions, I will reply shortly. Regards, Amar.
  14. 0
    Marcio Sampaio ·
    Amar,

    No problem. Tell me if it works after u try.

    Regards.

    Marcio Eduardo.
  15. 0
    Amar Aghana ·
    Marcio, Dinesh,

    I created job services. But it did not work. What is service Pack? How do I check, that is available?
  16. 0
    Kevin Button ·
    Amar

    Just a thought - has the Job Services software been installed onto your server? If you check the document titled adminguide.pdf on your documentation CD it will explain the steps to install and start job services.

    Regards
  17. 0
    Amar Aghana ·
    Kevin, I read the matter. However, I do not think, this explains about backing up the data. Cheers, Amar.
  18. 0
    Kevin Button ·
    Amar

    I was just thinking that if your Job Services are not working you should check that the module was installed in the first place, because Job Services is not automatically installed when you install the database.

    Cheers
  19. 0
    Kevin Button ·
    Yes, 4.1 has Job Services.

    Cheers
  20. 0
    Kevin Button ·
    In V4.1 you can use Job Services to export any or all projects.
  21. 0
    Marcio Sampaio ·
    Amar,

    I suggest u to be in contact with IT department of your company. Maybe they have the CD of Service Pack. It’s too simple to install. Or be in contact with Primavera Systems and require the CD. It wighs like 140 MB.

    If u can’t, we can think about send u the CD. I don’t know if it’s correct. For me, Service Pack is a free reprodution.

    Regards.

    Marcio Eduardo.
    Rio de Janeiro - Brazil
  22. 0
    Marcio Sampaio ·
    Kevin,

    Did u read my explanation to do "Job Service"?

    Is it correct?

    Regards.

    Marcio Eduardo.
    Rio de Janeiro - Brazil.
  23. 0
    Kevin Button ·
    Marcio

    Your explanation looks OK to me

    Cheers

Log in or join to reply