Formatting / Split Tasks
In the Open Standard
Steven WilliamsMember for 21 years 5 months
- Created
- 4
- 3
0
I am currently preparing a claim document programme tracing issue of Isometric drawings through all revisions against a target issue date using P3e. I have at the moment each issue as a seperate activity, which is giving me an average of 18 activities to represent the history of the issue of 1 isometric.
This is poor as a presentation document, ideally i would like to use a SPLIT TASK function to show all issues on 1 line.
Does anybody know if this can be done (a la MS Project), but with the ability to format the splits bars sperate sections with colour and text???
I know this can be done with Artemis, but would ideally rather stay in P3e so as not to double handle info.
Secondly, if i was to summarise all info for each isometric, can this summary bar be formatted to achieve the same result ???
This is poor as a presentation document, ideally i would like to use a SPLIT TASK function to show all issues on 1 line.
Does anybody know if this can be done (a la MS Project), but with the ability to format the splits bars sperate sections with colour and text???
I know this can be done with Artemis, but would ideally rather stay in P3e so as not to double handle info.
Secondly, if i was to summarise all info for each isometric, can this summary bar be formatted to achieve the same result ???
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?