V5 : Copy and Paste : Auto Increment

Amar AghanaMember for 21 years 2 months
Created
4
4
0
Do we have Auto Increment of Activity IDs as used to be in P3?

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    Enterprise, Projects, Defaults Tab on the bottom layout
  2. 0
    Amar Aghana ·
    I am sorry. My question was Auto increment while copying and pasting.

    When we copy and paste in P3, It asks for auto increment, renaming etc.

    What is the alternate in V5.

    Cheers, Amar.
  3. 0
    Dinesh Kumar Damavarapu ·
    Hi,

    P3E does not ask for that options.It automatically adds the activity ID based on the defaults and location.

    Regards

    Dinesh
  4. 0
    Amar Aghana ·
    Dinesh, You are right, In the default tab, some option is available. But the advantage with this is limited. HTH, Amar.

Log in or join to reply