Dear All,

I’m trying to do a filter that shows activities that will be happening during three months. Not from the Data Date or Current Date (e.g. jan-06 / feb-06 / mar-06).

Any idea??

Can i use the sentence Custom Date+3M??

Regards.

Marcio Eduardo.

2 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Just one more thing ...

    The filter has to show activities that starts before and have progress between the three months; activities that happens between the three months and activities that starts between and finish after the third month.

    Regards.

    Marcio eduardo