Changing the Projects Time Period

Mario PatelMember for 22 years 6 months
Created
6
1
0
Can anybody advise me how I can change the period of time in my project i.e. 1 year to 2 years in an existing P3e programme?

6 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    Sorry Mario,

    I cant understand what are u trying to do.

    Do u have a timeschedule with 1 year durarion and whant to become it 2 years durarion, ok??

    Does this timeschedule has any progress? Or it didnt start yet?

    Probably u will have to change activity durations to achive 2 years, or detail more WBS inserting more activities etc.

    My first impression is that u are replanning your project. Is that ok??

    Regards.

    Marcio Eduardo.
  2. 0
    Mario Patel ·
    My existing project has a project start date of April ’05 and a project finish date of March’06. I have now added in activities for April ’06. These activities are showing critical. My guess is that this is due to the project finish date.

    I figured if I could change the project finish date it would sort out the activities that are showing critical.
  3. 0
    Marcio Sampaio ·
    Ok Mario,

    Go on PROJECT view > DATES > and change MUST FINISH BY.

    Hope it can help u.

    Best regards,

    Marcio Eduardo.
    Rio de Janeiro - Brazil.
  4. 0
    Mario Patel ·
    I don’t have that option.
    If I click on PROJECT-

    Activities
    Resource Assignments
    WBS
    ______________
    Baseline
    Expenses
    Work Products and Documents
    ______________

    Threshold
    Issues
    Risks
    _______________
    Set Default Project
  5. 0
    Mario Patel ·
    Thank You very much for your guidance. I finally worked out what you meant.
  6. 0
    Marcio Sampaio ·
    Glad to help.

Log in or join to reply